| ===  | === status === | ||
| * available from: '''2012-07-01''' | |||
| Called the contact person. [[user:martian742]] | Called the contact person. [[user:martian742]] | ||
| Line 8: | Line 9: | ||
| We're supposed to call back near 2012-07-01, because right now, everything is occupied. | We're supposed to call back near 2012-07-01, because right now, everything is occupied. | ||
| Then we can be presented with rooms ~ | Then we can be presented with rooms ~34m2 big, each, not necessarily connected/adjacent, but internal walls' demolition possible. :) | ||
| What I should find out about is '''the price'''.. | |||
| === pros === | |||
| * close to some member's workpaces/homes | |||
| === parameters === | |||
| * wooden buildings, "linkusák" in Czech | |||
| * rooms ~34m2 big, office-type, but dirty/loud work allowed | |||
| ** there are people already, doing reverse osmosis & PC water-cooler machining | |||
| * central heating by 2 gas boilers distributed by radiators in the rooms | |||
| * no air-conditioning, unlike in Brmlab's industrial space | |||
Revision as of 08:10, 12 June 2012
status
- available from: 2012-07-01
Called the contact person. user:martian742
The only buildings available in that area are the wooden ones closest to the old fighter aircraft.
We're supposed to call back near 2012-07-01, because right now, everything is occupied.
Then we can be presented with rooms ~34m2 big, each, not necessarily connected/adjacent, but internal walls' demolition possible. :)
What I should find out about is the price..
pros
- close to some member's workpaces/homes
parameters
- wooden buildings, "linkusák" in Czech
- rooms ~34m2 big, office-type, but dirty/loud work allowed
- there are people already, doing reverse osmosis & PC water-cooler machining
 
- central heating by 2 gas boilers distributed by radiators in the rooms
- no air-conditioning, unlike in Brmlab's industrial space